Until the April 2019 period, PT PII has guaranteed 20 infrastructure projects consisting of 10 toll road projects, 4 telecommunications projects, 1 Railway Transportation Project, 1 Power Plant Project, 3 Water Supply System projects and 1 Non-PPP Project.

Ringkasan Penjaminan

PT PII

Belum Konstruksi Proses Konstruksi Konstruksi Selesai(COD)
No Proyek Jenis Proyek Nilai Proyek (RP Miliar) Maks Guarantee (RP Miliar) Karakteristik Proyek Skema Durasi Penjaminan (Setelah COD) Penjaminan Bersama MOF Project Progress
1 CJPP PSN 61,456 300 Kapasitas: 2 x 1000 MW BOT 21 Tahun Ya
2 SPAM Umbulan PSN, PPN

2.057

1.170

Kapasitas produksi: 4000 lpd

SBOT (VGF,DK) 15 Tahun Tidak
3 Palapa Ring Barat PSN

1.229

1.293

Fiber Optik: 1.980 km

AP 12 Tahun Tidak
4 Palapa Ring Tengah PSN

1.093

1.211

Fiber Optik: 2.647 km

AP 12 Tahun Tidak
5 Palapa Ring Timur PSN

5,088

5,467

Fiber Optik: 6.224 km

Microwave : 76 sites

AP 12 Tahun Tidak
6 Tol Batang Semarang PSN, PPN

11,046

2,450

Panjang jalan: 77,6 km

BOT 15 Tahun Tidak
7 Tol Pandaan Malang PSN

5,970

5,623

Panjang jalan: 38,7 km

BOT 15 Tahun Tidak
8 Tol Manado Bitung PSN, PPN

5,123

3,400

Panjang jalan: 39,9 km

SBOT (VGF,DK) 15 Tahun Tidak
9 Tol Balikpapan Samarinda PSN, PPN

9,973

6,120

Panjang jalan: 99,3 km

SBOT (VGF,DK) 15 Tahun Tidak
10 Tol Jakarta Cikampex II Elevated -

16,233

600

Panjang jalan: 36,4 km

BOT 15 Tahun Ya
11 Tol Krian Bunder PSN

12,224

649

Panjang jalan: 38,2 km

BOT 15 Tahun Ya
12 Serang Panimbang PSN

5.330

1,443

Panjang jalan: 83,9 km

SBOT (VGF,DK) 15 Tahun Ya
13 Cileunyi Dawunan PSN

8.409

1,430

Panjang jalan: 60,3 km

SBOT (VGF,DK) 15 Tahun Ya
14 Tol Probolinggo Banyuwangi PSN 23,391 2,281 Panjang Jalan : 172.9 Km BOT 15 Tahun Ya
15 Tol Jakarta Cikampek II - Selatan PSN 14,691 2,280 Panjang Jalan : 62.95 Km BOT 15 Tahun Ya
16 SPAM Bandar Lampung PSN 750 543 Kapasitas produksi: 750 lpd SBOT(VGF,DK) 15 Tahun Tidak
17 SPAM Semarang Barat PSN 417 631 Kapasitas produksi: 1000 lpd BOT 15 Tahun Tidak
18 KEK Mandalika Non KPBU 4,569 1,366 Pengembangan Lahan Seluas 1,175 Ha Direct Landing 25 Tahun Ya
19 Kereta Api Makassar - Parepare PSN 1,100 - Panjang Mainline Track 142,0 Km AP 18,5 Tahun Ya
20 Satelit Multifungsi PSN 21,000 - Kapasitas 150 Gbps AP 15 Tahun Ya

 


 

No Proyek Lokasi Signing PKS Signing GA Financial Close Efektif Penjaminan Target COD PJPK Nama Badan Usaha
1 CJPP Kab. Batang Jawa Tengah 06-Oct-11 06-Oct-11 03-Jun-16 06-Jun-16 Unit 1 (May 31, 2020)
Unit 2 (Nov 30, 2020)
PT PLN (Persero) PT Bhimasena Power Indonesia
2 SPAM Umbulan Jawa Timur

21-Jul-16

21-Jul-16

10-Feb-17

10-Feb-17

Awal 2019

Pemerintah Provinsi Jawa Timur

PT Meta Adhya Tirta Umbulan

3 Palapa Ring Barat Indonesia Bagian Barat

29-Feb-16

29-Feb-16

25-Jul-16

10-Nov-16

Q1 2018

Kementerian Komunikasi dan Informatika

PT Palapa Ring Barat

4 Palapa Ring Tengah Indonesia Bagian Tengah

04-Mar-16

04-Mar-16

29-Sep-16

10-Jan-17

Q1 2018

Kementerian Komunikasi dan Informatika

PT Len Telekomunikasi Indonesia

5 Palapa Ring Timur Indonesia Bagian Timur

29-Sep-16

29-Sep-16

Est.
27-Mar-2017

Est.
27 Mar 2017

Q3 2018

Kementerian Komunikasi dan Informatika

PT  Palapa Timur Telematika

6 Tol Barang Semarang Barang Semarang

27-Apr-16

27-Apr-16

Turnkey contract

20-Jun-16

Mid 2018

Kementerian PUPR

PT Jasamarga Semarang Batang

7 Tol Pandaan Malang Pandaan Malang

10-Jun-16

10-Jun-16

Turnkey contract

03-Oct-16

Awal 2019

Kementerian PUPR

PT Jasamarga Pandaan Malang

8 Tol Manado Bitung Manado Bitung

10-Jun-16

10-Jun-16

Turnkey contract

06-Oct-16

Akhir 2019

Kementerian PUPR

PT Jasamarga Manado Bitung

9 Tol Balikpapan Samarinda Balikpapan Samarinda

10-Jun-16

10-Jun-16

Turnkey contract

02-Dec-16

Akhir 2018

Kementerian PUPR

PT Jasamarga Balikpapan Samarinda

10 Tol Jakarta Cikampek II Elevated Jakarta Cikampek II Elevated

06-Dec-16

22-Feb-17

Turnkey contract

22-Feb-17

Awal 2019

Kementerian PUPR

PT Jasamarga Jalan Layang Cikampek

11 Tol Krian Bunder Krian Bunder

06-Dec-16

22-Feb-17

Turnkey contract

Est. 25-Mar-17

Mid 2019

Kementerian PUPR

PT Waskita Bumi Wira

12 Tol Serang Panimbang Serang Panimbang

22-Feb-17

22-Feb-17

Turnkey contract

Est. 25-Mar-17

Mid 2019

Kementerian PUPR

PT Wijaya Karya Serang Panimbang

13 Tol Cileunyi Dawunan Cileunyi Dawunan

22-Feb-17

22-Feb-17

Turnkey contract

Est. 25-Mar-17

Mid 2019

Kementerian PUPR

PT Citra Karya Jabar Tol

14 Tol Probolinggo Banyuwangi Jawa Timur 29-Des-17 22-Des-2017 Des 2018 Belum Efektif Des 2019 Kementerian PUPR PT Jasamarga Probolinggo Banyuwangi
15 Tol Jakarta Cikampek II Selatan Jakarta Cikampek 29-Des-17 22-Des-17 Des 2018 Belum Efektif Des 2019 Kementerian PUPR PT Jasamarga Japek Selatan
16 SPAM Bandar Lampung Bandar Lampung - 14-Feb-2018 Feb 2019 Belum Efektif Feb 2020 Pemprov Bandar Lampung PT Meta Adhya Tirta Lampung
17 SPAM Semarang Barat Semarang - 23-Nov-2018 - - - PT Air Semarang Barat PT Tirta Moedal
18 KEK Mandalika Lombok - 31-Des-2018 - - - - Indonesia Tourism Development Corporation) ITDC
19 Kereta Api Makassar - Parepare Makassar - 6-April-2019 - - - Kementerian Perhubungan

PT Celebes Railway Indonesia

20 Satelit Multifungsi Jakarta - 3-Mei-2019 - - - Kementerian Komunikasi dan Informatika PT Satelit Nusantara Tiga